The Ministry of Energy of Uzbekistan reported that the new 500/220 kV substation, which was being built at the thermal power plant in Navoi, has received initial voltage on the 220 kV busbars.
These works are part of an investment project aimed at constructing a third 650 MW combined cycle gas turbine unit at this power plant. After commissioning, the power plant and a 300 MW hybrid solar photovoltaic power plant were connected via the new substation.
This infrastructure is designed to strengthen electrical connections between the southwestern and northern parts of Uzbekistan's unified power system. Furthermore, an increase in the reliability of electricity transmission through high-voltage grids and an improvement in the stability of the entire energy system are expected.
Modern equipment from Japan, China, India, and South Korea is being installed at the substation to ensure technical performance and reliability. The general contractor for the project is a consortium including Japanese companies Mitsubishi Corporation and Mitsubishi Power Ltd, while the Turkish company Calik Enerji participates as a subcontractor.
The next stage involves commissioning the equipment necessary to transmit electricity from the new combined cycle gas turbine unit into the national power system. This will allow for final checks and inspections of the unit before its gradual introduction into operation.