The first phase of the comprehensive reconstruction of Mustakillik Avenue in the Mirzo-Ulubek district of Tashkent is drawing to a close. According to data from the Capital Traffic Management Center (TSODD), work on restoring the pavement on one section has been completed, and traffic is expected to resume there shortly.
Road Pavement Works
During the work, specialists dismantled 23,000 square meters of worn road surface and replaced it with an equal volume of crushed stone-asphalt concrete. Additionally, basalt geogrid was installed over an area of approximately 29,000 square meters to strengthen the road structure.
Currently, road crews are laying the top wear-resistant layer, SMA-20 (polymer-modified stone asphalt), on a 23,000 square meter section. Representatives of TSODD noted that this material provides high resistance to heavy vehicle loads, deformation at high temperatures, and rutting, which will significantly extend the service life of the avenue's pavement.
Drainage System Modernization
Concurrently, the modernization of the stormwater drainage system along the route is underway. Crews have repaired 1.14 kilometers of drainage gutters, replaced 111 meters of metal pipes, installed 1.3 kilometers of new curbs, and replaced another 1.14 kilometers of edge stones along the main carriageway. Furthermore, 566 meters of old curb stones were dismantled along the central dividing lane.
According to TSODD, these drainage improvements will reduce the likelihood of water accumulation on the road during heavy rains, thereby protecting the new asphalt pavement from water damage.
Avenue Infrastructure Update
The street lighting network on the avenue is also being updated: plans include replacing 34 outdated lampposts with 67 modern ones. In addition, three bus platforms are being constructed, and three new bus stops are being installed. Passenger waiting areas are being expanded and equipped with tactile paving tiles to assist visually impaired pedestrians.
The current reconstruction project involves over 30 units of specialized equipment, as well as more than 250 workers and specialists.
Traffic Schedule and Delays
Traffic on the Mustakillik Avenue section between Mirzo Ulugbek Street and Akkurgan Street towards the city center was initially restricted until July 13, 2026, for repair work in the capital. However, unforeseen requirements for the major repair of drainage and runoff systems prevented contractors from completing the work within the originally stated timeframe.