The reconstruction of Woodlands Primary School in Pietermaritzburg has officially begun, marking a significant turning point for both the educational institution and the KwaZulu-Natal Department of Public Works and Infrastructure. Work on new brick buildings, which will replace old buildings with lead roofs, is resuming after a two-year break caused by contract payment disputes.
Departmental Recovery
The Minister of Public Works and Infrastructure for KwaZulu-Natal, Martin Meyer, stated that the last two years were dedicated to revitalizing the department, and Woodlands Primary School is part of this process. He emphasized that the goal is for the school to serve as an example of the department's successful transformation, demonstrating how it learned from mistakes and changed its approach to construction.
Meyer clarified that the previous contractor left the site due to non-payment from the department. He reported that a forensic audit was conducted, which found no criminal activity or negligence; the issue was solely related to untimely payment from the client to the contractor. These matters, he said, are now resolved.
Financial and External Factors
The two-year standstill requires an additional 43 million, exceeding the initial budget, because the site needs to be prepared again. Furthermore, Meyer noted changes in global conditions, including invasions by other countries, as well as rising fuel and construction material prices, which made the initial estimates inaccurate.
School and Contractor Positions
Woodlands School Principal, Claudelle Manuel, shared that the school has been in its current state for over 50 years. She thanked Meyer for prioritizing the project, noting that the school had faced issues such as declining enrollment, flooding during rain, and dust on windy days. She expressed hope for the project's completion with the new contractor.
Contractor Zibonephi Projects & Business Enterprise, Mboniseni Ndlovu, assured that they will ensure high-quality execution of the project within 15 months. He divided the work into four phases, the first taking three months, the second another four to five months, and the third and fourth phases taking the remaining time.
Community Requirements and Support
Ward Councillor 32, Garth Middleton, noted that three or four years have passed and urged ensuring budget reserves to prevent delays in payments to contractors, subcontractors, and staff of the Expanded Public Works Programme on site. The Deputy CEO of the KwaZulu-Natal Department of Public Works and Infrastructure, Tobuize Mchunu, praised the Woodlands community for safeguarding materials on site, noting that even installed electrical equipment remained in place during the two-year absence of the contractor.