Megha Engineering & Infrastructures Ltd (MEIL) announced on Monday the completion of concrete pouring for the Pressurized Heavy Water Reactor (PHWR) program at Kaiga 5 and 6 sites in the nuclear power plant project in Karnataka state.
Scale of Construction Work
This operation involved placing approximately 7,250 cubic meters of concrete with a rebar density of 360 kg per cubic meter, marking a significant milestone in the construction of both units. The first phase of concrete pouring took place in March 2026, officially commencing the construction of two 700 MW PHWR reactors at this site.
Criticality Schedule
According to the Department of Atomic Energy, Kaiga-5 is expected to reach criticality approximately five years after the initial concrete pour, which is in 2031.
Technical Aspects of the Project
MEIL was able to achieve a production capacity for temperature-controlled concrete output of 360 cubic meters per hour. The company maintained the concrete placement temperature at 19 degrees Celsius and utilized concrete pumps with a capacity of 340 cubic meters per hour. To ensure thermal control and cooling of the mix, an ice production capacity of 510 tons per day was established, along with an ice storage facility of 400 metric tons, and a joint storage facility for cement and fly ash of 2,600 metric tons.
